• By clicking on the following items you can view for each part of the project the start of work date, the progress of the work and the expected completion date.

    Last update: 1st of October 2017 

  • START OF WORK: 2009
    % PROGRESS: 100%
    CURRENT STAGE: completed
    COMPLETION: 2013

  • START OF WORK: 2009
    % PROGRESS: 100%
    CURRENT STAGE: completed
    COMPLETION: 2013

  • START OF WORK: 2012
    % PROGRESS: 100%
    CURRENT STAGE: completed
    COMPLETION : 2015

  • START OF WORK: 2013
    % PROGRESS: 90%
    CURRENT STAGE: cladding completed, currently underway the connection between tower and podium. Finishing and systems installation in progress.
    EXPECTED COMPLETION: Q4 2017

  • START OF WORK: 2015
    % PROGRESS: 20%
    CURRENT STAGE: finishings and systems installation in progress (underground levels)
    EXPECTED COMPLETION: Q1 2020

  • START OF WORK: 2013
    % PROGRESS: 90%
    CURRENT STAGE: facades and systems installation almost completed. Currently underway stores fit out
    EXPECTED COMPLETION: Q4 2017

  • PARK (FIRST PORTION) – 76,000 SQM
    START OF WORK: 2013
    % PROGRESS: 100%
    CURRENT STAGE: completed
    COMPLETION: 2015

  • PARK (Phase 4) - 17,500 SQM
    EXPECTED START OF WORK: Q2 2017
    % PROGRESS: 60%
    CURRENT STAGE: work in progress
    EXPECTED COMPLETION: Q4 2017

  • PARK (Phase 5) - 24,000 SQM
    START OF WORK:  Q2 2017
    % PROGRESS: 65%
    CURRENT STAGE: work in progress
    EXPECTED COMPLETION: Q4 2017

  • PARK (Phase 6) - 55,500 MQ
    EXPECTED START OF WORK: 2018
    % PROGRESS: 0%
    CURRENT STAGE: under design
    EXPECTED COMPLETION: Q3 2019

  • START OF WORK: Q2 2017
    % PROGRESS: 15%
    CURRENT STAGE: work in progress
    EXPECTED COMPLETION: Q2 2018

  • START OF WORK: Q4 2016
    % PROGRESS: 75%
    CURRENT STAGE: work in progress
    EXPECTED COMPLETION: Q4 2017

  • UNDERGROUND LINE (WORK AS PERTAINING TO CITYLIFE)
    START OF WORK: 2010
    % PROGRESS: 100%
    CURRENT STAGE: external structure delivered to M5
    COMPLETION: 2012

  • Working progress

  • Residences designed by Daniel Libeskind
  • Residences designed by Zaha Hadid
  • Allianz Tower
  • Generali Tower
  • Libeskind Tower
  • Shopping District
  • Park (Portion completed)
  • Park - C1
  • Park - B2
  • Park - C2
  • Nursery
  • Padiglione 3 - Facades
  • Col metroUnderground line